ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE VENICE HIGH SCHOOL: BUSINESS TECHNOLOGY BUILDING 31 - C.T.E. LABORATORY IN ROOMS 001 & 002 PROJECT

Description
The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.

Recommendation
That the work performed by McIntyre Elwell & Strammer General Contractors, Inc. for the Venice High School - Business Technology Building 31 C.T.E. Laboratory in Rooms 001 & 002 project be accepted as substantially complete as of 7/9/2008.

Contact
LEMPE & COLLINS

Financial Impact
N/A


Attachment:  BAIenc10-07-08VHS-BusTechBldg31CTE-LabRms1&2SC.pdf